Brisbane Metro delayed as land deal drags on

Ruth McCosker

A gap of almost $7 million in the Brisbane Metro budget has revealed the first stages of the project have been delayed.

The Brisbane City Council’s quarterly financial report revealed $6.9 million was underspent for the quarter's projected spend towards the $944 million project.

Brisbane City Council's Brisbane Metro is expected to cost $944 million.BCC

In October the council announced the next step in the project was to buy two crucial parcels of land that were owned by the state government.

The first parcel of land is a 1600-square-metre lot on Grey Street at South Brisbane, beside the bus station, and the second is a 4.5-hectare block of land at Rochedale.

Advertisement

The land was needed for the construction of an underground busway at South Brisbane and for the Rochedale depot for the 60 Brisbane Metro “articulated buses”.

Shadow transport planning spokesman Jared Cassidy said he did not believe the council or public transport chairman Adrian Schrinner had even approached the state government, a claim Cr Schrinner refuted.

“He [Cr Schrinner] talks about it all the time, but he never produces any hard evidence that he’s actually working with the state government or that council has actually made a proper approach to purchase this land,” Cr Cassidy said.

“I don’t think this $7 million delay in the Brisbane Metro project has anything to do with that.

“Perhaps they’re having cold feet on their super banana bus project, as we’re seeing delay after delay after delay.”

Advertisement
A 4.5-hectare site at Rochedale is being bought by BCC to allow the new Metro vehicles to begin and end their routes close to the South East Busway.

Cr Schrinner said Cr Cassidy’s claim was "bizarre" and he produced letters sent between the council and state government.

“I don’t know why he asked that question or why he made that suggestion,” he said.

Letters seen by Fairfax Media revealed Cr Schrinner wrote to Deputy Premier Jackie Trad on September 27, 2017, about the state land requirements for Brisbane Metro.

“I am writing to request the Queensland government to assist in the delivery of Brisbane Metro by contributing state-owned land to the project,” the letter said.

Advertisement

Ms Trad wrote a return letter to Cr Schrinner on October 16.

The letter said a cross-government review of the business case was being progressed.

“With respect to the transfer of state lands, the Queensland government will be in a position to provide a response to your request following consideration of the business case,” the letter said.

Cr Schrinner said the council was keen to continue with the Brisbane Metro but had not yet been able to purchase the land.

“That $6.9 million was an anticipated payment for state government-owned land that we need for the project and unfortunately we haven’t been able to purchase that land,” he said.

Advertisement

“The state has been dragging their feet.

“These letters quite clearly show that we have asked, we’ve actually gone to the top of the government, the Deputy Premier, the person who is in charge, and we are still waiting for an outcome to that request.”

State opposition transport spokesman Steve Minnikin said the Premier was "stalling on a project which will take 125 buses off of congested CBD streets".

"At the last election, the LNP said it would gift this surplus land to the Brisbane Metro project to improve public transport in the city."

Ruth McCoskerRuth McCosker is former reporter at the Brisbane Times.